Projects - Upgrading of Water Supply System for Garri Power Plant (Sudan)

Project Description

725213_WSsudan

 

LOCATION
Garri, Khartoum North, Republic of the Sudan

OWNER
National Electricity Corporation (NEC), Republic of the Sudan and EGCO Engineering & Service Co., Ltd.

DESCRIPTION
The study is to improve water supply production system and increase quantity and quality of water to meet water consumption of the power plants in the future and study guidelines to reduce existing operating cost. The system will supply water to Garri power plant  (No.I, II, and IV), a total capacity of 518 MW, at the rate of approximately 22,000 cu.m. per day, and planned power plant No.III of 540 MW. The water supply consumption of all power plants will be increased to 62,000 cu.m. per day.

SERVICE RENDERED
–  Study and propose guidelines to improve efficiency of the water supply system;
–  Guidelines to reduce the operating cost;
–  Develop training courses for water supply system operators in Bangkok. The  outcomes are satisfactory then the follow up and future studies are proposed for next phases.

DURATION
September 2009 – 2010