Projects - Study, Survey, and Design of Route No. SP4002 from TL.3344 Intersection – Ban Bang Phli Yai (Samut Prakan)

Project Description

505119_BangPhliYai

 

LOCATION
Bang Phli district, Samut Prakan province

OWNER
Department of Rural Roads, Ministry of Transport

DESCRIPTION
The improvement for widening a 2-lane to 4-lane or 6-lane highway of route No. SP 4002, started from Km. 0+000 at TL.3344 intersection to Km.7+934 at Ban Bang Phli Yai within 20-30 m. right of way and a length of 8 km. including road connections and landscaping.

CONSTRUCTION COST
1,400 million Baht (11.4 million USD) (1 USD : 35 Baht)

SERVICE RENDERED
–  Preliminary route survey, alternative route comparison and selection of the most feasible route;
–  Topographic and traffic survey;
–  Detailed engineering design;
–  Cost estimation and preparation of tender documents;
–  Environmental impact assessment.

DURATION
February – November 2009