LOCATION
Phaya Thai district; Huai Khwang district, Bangkok
OWNER
Department of Public Works and Town & Country Planning (DPT)
DESCRIPTION
The project is the energy management system development of government’s office building to achieve the successful and create standard of energy conservation in accordance with laws / regulations. The project comprises 2 building location; namely,
1.) At Rama VI road: 4 buildings, a total area of 45,632.6 sq.m., the energy consumption from:
– IElectric generator: 3 sets, a total capacity of 3,750 kVA.;
– Air-conditioner: 5 sets of centralized type and 196 units of split type;
– Electric lamp: 26,606 units.
2.) At Rama VI road: 7 buildings, a total area of 42,100 sq.m., the energy consumption from:
– Electric generator: 2 sets, a total capacity of 4,100 kVA.;
– Air-conditioner: 254 units of split type;
– Electric lamp: 3,663 units.
SERVICERENDERED
1. Advise the establishment of energy management committee;
2. Assess the energy management situation and energy conservation potential;
3. Set up the energy conservation policy, target, and plan;
4. Audit and analyze the implementation following the set up plan and target;
5. Monitor and evaluate the energy management;
6. Review, analyze, and resolve the energy management deficiencies.
DURATION
September 2013 – November 2013